File Code: Procurement
- Sponsored By:
-
Senator Trotter
- Entitled:
-
Construction Contracts - Cost Overruns
Altering a construction contract clause relating to contract
modifications or change orders to allow a contract modification or
change order that will increase the cost beyond budgeted and available
money only if the scope of the project is adjusted to allow completion
within the project budget.
Senate Action
- 11/13
- Pre-filed
- 1/8
- First Reading Economic and Environmental Affairs
- 1/3
- Hearing 1/23 at 1:00 p.m.
- 1/9
- Hearing cancelled
- Re-assigned Budget and Taxation
- 1/27
- Withdrawn
House Action
- No Action
- Bill indexed under the following Subjects:
- CONSTRUCTION
- CONTRACTS -see also- LAND INSTALLMENT CONTRACTS; PROCUREMENT
- PROCUREMENT
- Bill affects the following Statute:
- State Finance and Procurement
- (
13-218
)
- Bill Text:
- First Reading (PDF),
Third Reading, Enrolled
- Fiscal Note:
Not available at this time